Starship at Cape Canaveral making progress as SpaceX tries to push the 
program forward
Date:
Wed, 16 Jul 2025 21:16:41 +0000
Description:
While SpaceX continues to attempt to launch flight tests at Starbase, crews  are working diligently The post Starship at Cape Canaveral making progress as  SpaceX tries to push the program forward appeared first on 
NASASpaceFlight.com .
FULL STORY ======================================================================
 While SpaceX continues to attempt to launch flight tests at Starbase, crews  are working diligently to bring the next several pads and the next production  facility online. Roberts Road and LC-39A have seen significant progress, 
while demolition of SLC-37 continues. 
 Roberts Road 
 Over the past several months, SpaceX has been significantly expanding its  operations at the Roberts Road facility in Cape Canaveral. The foundation for  the first Gigbay has been a slow but intense project. 
 This project isnt as simple as the foundations for the Mega Bays, where  SpaceX drilled a set of piles and then poured the foundation. Which then  allowed crews to place pre-fabricated modular parts until it was the correct  height for the Mega Bays. 
 This building is far more advanced and complex; teams need to drill all of  the piles for the foundation and then dig out around those piles. This part 
is already completed. 
Next, crews will need to build a massive rebar box to fill the excavated 
area, which is still currently underway. Along with the rebar box, tons of  conduit and embeds will be installed to help start the initial installation 
of the steel columns and equipment needed for this structure. Gigabay  Foundation at Roberts Road (Credit: Joe B for NSF) 
 See Also SpaceX Starship Program L2 SpaceX Section NSF Store Click here to  Join L2 
Once all of this is completed, crews will then begin the concrete pour to 
fill in the foundation. So far, a single corner of this foundation has been  poured. Once the foundation is poured and cured, crews can then start to 
bring in the four tower cranes that will help assemble the Gigbay. These are  slated to be positioned in all four corners and will stick-build the bay 
until it is completed. 
 Stick building is a form of construction where one beam is lifted and 
secured in place at a time, unlike how SpaceX built the bays in Starbase with  prefabricated sections. It could take at least a year or so to construct this  bay, followed by the time to make all the internal workstations and work  platforms. 
 Gigbay will consist of 24 separate work stations laid out in four rows of  six. There will be two transfer aisles that span the entire length of the  building, separated by a central wall. This will enable SpaceX to bring  sections of new vehicles on one side and roll completed vehicles out of the  other. Roberts Road Facility with Launch Tower Construction Spots (Credit: 
Joe B for NSF) 
 To the south of the Gigaby construction site, SpaceX has completed nine new  launch tower construction pads and has since relocated most of the tower  construction materials to these new pads. With these new pads, and if SpaceX  continues to use the older pads, crews can build two launch towers  simultaneously. With the possibility of four towers at SLC-37 and possibly a  catch tower at LC-39A, SpaceX has the potential for at least five towers that  require fabrication. 
 Next door to the tower construction area is the launch mount for LC-39A. 
This launch mount has seen tons of progress over the past few months.  Currently, all but one section of the water-cooled steel deck plate has been  installed on the mount, as crews continue to make excellent progress. Based 
on progress on the launch mount and progress at LC-39A, the mount could roll  to the pad by October or November of this year. LC-39A OLM at Roberts Road  (Credit: Julia Bergeron for NSF) 
 LC-39A 
 SpaceX has made tons of progress on the Starship pad at LC-39A in the past  few months. The trench is currently fully dug out, with the rebar cage for 
the floor being constructed. Sheet piles are also being placed for the  commodities trench that will supply the service structure and the launch  mount. 
 Just behind the launch tower, crews have already placed a few water deluge  tanks and are starting to set up the water pipes that will eventually go to  the launch mount and flame deflector. To the east of the trench, SpaceX is  setting up two rows of horizontal tanks to accompany the Liquid Methane 
(LCH4) Sphere, which will supply propellant to Starship. These will hook into  what is likely to be a carbon copy of the same pump and subcooler setup 
SpaceX has installed for Pad 2 (B) at Starbase. LC-39A Starship Pad  Construction (Credit: Joe B for NSF) 
 This is nine Liquid Oxygen (LOX) Pumps and eight LCH4 Pumps, which will fill  the full stack. This setup will be placed in between the two rows of  propellant tanks and then fed into the commodities trench, which will then  split to the tower and the launch mount. 
 SpaceX has stated that LC-39A could be ready for checkouts by the end of  2025. However, based on timelines for Pad 2 (B) at Starbase and considering  the amount of work that remains to be completed, it is likely that this pad  wont be online until sometime in the middle of 2026. Tank Farm and Water  Deluge Equipment at Starbase Pad 2 (B) (Credit: Jack Beyer for NSF) 
 SLC-37 
 LC-39A is not the only Starship pad that SpaceX is planning to build at Cape  Canaveral. Just a few weeks ago, demolition crews destroyed the Delta IV  mobile integration and service structure. With the cleanup underway, SpaceX  will have to wait until the Environmental Impact Statement is completed for  SLC-37 before starting construction efforts for the next set of Starship  launch pads. 
 SLC-37 is planned to include two launch towers, with two possible catch  towers if space allows. These two launch pads would connect to a central tank  farm and, once completed, would bring the Starship Programs launch pads to  five. That number includes two launch pads at Starbase, one at LC-39A, and 
two at SLC-37. 
 With construction not even started since SpaceX doesnt have a lease 
agreement for the pad yet, this pad would likely not be ready for flight 
until late 2027 or 2028 at the earliest. SLC-37 Demolition and Cleanup Work  (Credit: Joe B for NSF) 
 Featured Image: Historic Launch Complex 39A (Credit: Julia Bergeron for NSF   100s of hi-res photos available to download for L2 members) 
 
The post Starship at Cape Canaveral making progress as SpaceX tries to push  the program forward appeared first on NASASpaceFlight.com .
======================================================================
Link to news story: 
https://www.nasaspaceflight.com/2025/07/starship-cape-canaveral-progress/
--- Mystic BBS v1.12 A47 (Linux/64)
 * Origin: tqwNet Science News (1337:1/100)